Systems Specifications Maintenance Repaint
Surface Preparation: No paint system will give optimum performance over poorly prepared surfaces. Painting over dirt, dust or contaminated surfaces is
wasteful in terms of time, materials and labour.
Ensure surfaces are degreased and free of contamination using Protective Paints A925 - Metal degreaser (follow instructions as per data sheet).
Ensure surfaces are free from preparation
debris and are clean and dry. Apply 1st coat within 4 hours of
abrasive blasting. Practical coverage is project dependent.
All corroless data sheets can be obtained by cicking on the links.
DFT = Dry Film Thickness WFT
= Wet Film thickness TDF = Total Dry Film thickness
Spec 020 - Alkyd System
for Mild Steel and Hot dipped Galvanizing
|
Internal / External Mild Exposure *5 - 8 years to first maintenance to AS/NZ 2312 |
Away from coast and industrial activity Power tool clean to rust effected area to AS 1627.2 Class 3 Abrade coating feathering edges removing gloss/chalking |
|
1st Coat |
Apply
Corroless S1 or S2 at 80 µ WFT (35 µ DFT)
|
|
2nd and 3rd coat |
Apply Corroless RF 15 at 120 µ WFT (60 µ DFT ) tinted to approved colour |
TDF = 155 microns minimum
Spec 021- Epoxy System 1 System
for Mild Steel over Colour Steel and Hot dipped Galvanizing
|
Internal / External Wet Exposure *8 – 10 years
to first maintenance to AS/NZ 2312 |
Preparation: Abrasive Blasting Sa 3 of AS 1627.9. Two pack system |
|
1st coat: |
Apply Corroless E at 90 µ WFT( 50 µ DFT) |
|
2nd and 3rd |
Apply Corroless RF 60 at 50 µ WFT ( 30 DFT) |
TDF = 110 microns minimum
Spec 022 - Epoxy System 2 System
for Mild Steel and Hot dipped Galvanizing
|
External/Coastal
Marine Exposure *13 – 15 years to first maintenance to AS/NZ 2312 |
Less Than 10 km from coastal areas of industrial activity Power tool clean to rust effected area to AS 1627.2 Class 3 Abrade coating feathering edges removing gloss/chalking |
|
1st coat: |
Apply Corroless EP at 210 µ WFT( 200 µ DFT) |
|
2nd and 3rd |
Apply Corroless RF 60 at 50 µ WFT ( 30 DFT) tinted to approved colour |
TDF = 260 microns minimum
Specification subject to NZS/AS 1627; Preparation of surfaces NZS/AS
2312 Protection of mild steel; AS 3894 Determination of Dry Film thickness
*General Metal Protection
and Maintenance Schedule:
The main task of the protective coatings is to prevent or control corrosion. During its service life a protection coating system deteriorates
as
a result of exposure to ultra violet light, moisture, fluctuating temperatures,
chemicals, abrasion and many other possible factors.
It is thus recommended that a preventative maintenance schedule be
followed to attain the optimum performance from the coating system.